posted in: Trail News 0

According to David Toland, “construction of the 1.5 miles of the Prairie Spirit Trail Extension within the city limits of Iola is ahead of schedule. All of the concrete curb cuts have been completed on the extension within Iola thanks to the good weather, and nearly all of the lighting is in place, along with the bollards. The contractors should start laying asphalt this month.

Also, a Kansas Health Foundation Recognition Grant was recently awarded. It includes $7,329 for crosswalk signs, and way-finding signs to direct PSRT users to healthy lifestyles amenities and facilities within Iola. These will all be done as part of implementation of the Vision Iola Built Environment Plan.”